ROTTNEST ISLAND WATER PUMPING STATION

ROTTNEST ISLAND WATER PUMPING STATION

Client:  Programmed Facility Management
 Contract details:

Due to excessive hydraulic water hammer in piping in the line from the new waste water treatment plant to the surrounding irrigation on Rottnest island, the existing pipe ruptured causing a flood from the re-use water tank. Once isolated, WATMAR mobilized to assess the damage and strategies a prompt and permanent solution.

WATMAR where then contracted to construct a stainless steel pipe with dampening bellows and to re-adjust the pneumatic system.

 Time of contract: 24/09/2018
 The project outcomes: A new piping system was manufactured and installed within a week and the system has since been up and running smoothly in time for the warmer months.